01The hour before concrete
Pre-Pour Structural Verification
Formwork dimensions, slab thickness, bar size, spacing, cover, laps, chairs, embeds, anchor bolts and sleeves — and the pour volume, so nobody over-orders.
Pre-pour structural →
The category
Construction buries its own evidence on a schedule. Concrete covers steel. Grout fills cells. Drywall closes walls. Cladding hides the barrier. Every one of those moments is a deadline on a measurement nobody took. Alignmet flies the deadline.
Why the window matters
A tradesman moves it. Minutes, no paperwork, no schedule impact.
Cut, patch, re-inspect. A day of labour and a delayed follow-on trade.
Demolition of finished work, a repair detail, and a CO on hold.
Claim, expert reports, remediation through an occupied building.
Rework costs US construction on the order of $65B a year, and the average North American construction dispute runs into the tens of millions. Almost none of it is caused by things nobody could have seen — it is caused by things nobody looked at in the one hour they were still visible.
The flagship five
01The hour before concrete
Formwork dimensions, slab thickness, bar size, spacing, cover, laps, chairs, embeds, anchor bolts and sleeves — and the pour volume, so nobody over-orders.
Pre-pour structural →
02Before the grout pump arrives
Vertical bar cells, bar size, spacing, laps, anchorage, bond beams, opening sizes, wall plumb and straightness — inside every open cell before it fills.
CMU pre-grout →
03Before board goes up
Plumbing and fitting sizes, conduit and box heights, duct and sprinkler routing, blocking, insulation and firestopping — plus a permanent record of every cavity.
Pre-drywall MEP →
04Any floor, any week
As-built versus as-drawn: dimensional deviation, floor flatness and levelness, ceiling heights, clearances and accessibility compliance, as numbers per room.
Scan-to-BIM →
05Every milestone, all job long
The whole calendar of cover-up moments run as a standing program — every burial milestone flown, measured and archived, with one exception list per morning.
You are hereAlso in the program
06Before cladding and fireproofing
Anchor bolts, column plumb, bay dimensions, top-of-steel elevations, bolt counts at every connection, weld coverage and deck placement.
Structural steel →
07Before cladding covers the barrier
Waterproofing and air barrier continuity, flashing laps, windows and curtain wall, sealant joints, cladding attachment, roofing details and thermal moisture.
Envelope & facade →The burial calendar
| Milestone | What is still visible | Window closes |
|---|---|---|
| Slab on grade | Vapor barrier, rebar mats, embeds, sleeves | Buried by the pour |
| Elevated deck | Top and bottom mats, cover, chairs, post-tension | Buried by the pour |
| Columns & walls | Cage geometry, ties, laps, cover | Buried by the pour |
| CMU wall | Cell steel, laps, bond beams, anchorage | Buried by grout |
| Steel frame | Bolt counts, welds, plumb, bay dimensions | Buried by fireproofing and cladding |
| Envelope | WRB, air barrier, flashing laps, terminations | Buried by cladding |
| Wall cavity | MEP routing, blocking, insulation, firestop | Buried by drywall |
| Ceiling plenum | Duct, sprinkler, conduit, hangers, clearances | Buried by the grid |
| Underground | Under-slab plumbing and conduit routing | Buried by backfill |
| Roof assembly | Membrane laps, penetrations, curbs, drains | Buried by ballast and pavers |
How the program runs
The three-week schedule tells us which cover-up milestones land when.
Autonomous flights run before the crews arrive — no stand-down, no escort.
One list per milestone, per foreman, in hand before the trade starts.
Dated point cloud and imagery archived for every buried assembly.
What it costs when nobody's watching
~$65B / yr
U.S. construction rework cost — about 5% of $1.3T in total construction spend.
Source: Autodesk / FMI, Harnessing the Data Advantage in Construction (2020/2022)
~$31B / yr
rework tied to bad, missing or wrong project data — 48% of all rework traced to poor communication.
Source: PlanGrid / FMI, Construction Disconnected (2018, ~600 professionals surveyed)
5–9%
of total project cost lost to rework on a typical job; 20–30% on troubled projects.
Source: CII; Dodge Data & Analytics, SmartMarket Report on Project Rework (2018)
52%
of total cost overrun on a project traces back to rework.
Source: CII, analysis of 150+ industrial construction projects
$60.1M · 12.5 months
average U.S. construction dispute value and time to resolve.
Source: Arcadis, 2025 Global Construction Disputes Report
$15.8B / yr
industry-wide cost of poor data and system interoperability.
Source: NIST GCR 04-867 / NIBS (2004) — historical baseline, not current-year
389
fatal falls in U.S. construction in 2024 — 38% of all construction fatalities, 95.9% falls to a lower level.
Source: BLS, Census of Fatal Occupational Injuries 2024 (released Feb 2026)
$35K–$42K · $1.3M+
direct cost of a lost-time injury, and total cost of a fatal work injury.
Source: National Safety Council, Injury Facts
est. $300M–$1B / yr
U.S. construction equipment theft, under 25% recovered; ~$30,000 average per incident.
Source: DOE data via 2025–2026 security roundups; National Equipment Register / NICB (2014 baseline)
Government-grade sources (BLS, OSHA, NIST/NIBS) are cited as published. Industry research (Arcadis, FMI/Autodesk, CII, NSC) is survey- and estimate-based. Vendor case studies and vendor pricing pages are labeled where used and should be read as documented examples, not industry averages.
Ready to schedule a flight?
Click to reveal our direct sales email.